This short research note is an initial summary of the key changes between the Draft and the Final 2022 ISP.
Key takeaways:
- A significant number of inter- and intra-regional network augmentations have been delayed in the Final ISP compared to the Draft ISP
- Most of these network delays are only 1-2 years
- Northern QLD has seen the largest set of changes with respect to network upgrade timings